603619
Stock code
(%)
Up to 31 March, ZPEC Drilling opened drilling 19 wells, finished 11 wells, drilling depth was up to 38066 meters, 3835 meters more than the same time of last year, successfully finished this years working task and made a good beginning.
From 16 February to 15 March, ZPEC Drilling changed a set of BOP, racking board equipment, H2O and CO2 detector and anti-explosion devices etc. According to HSE, the company carefully checked the manufacturing site and added employee relative trainings. Meanwhile, deferent departments initiatively contacted with users and business partners. Even the climate of this year was changeable and always raining and snowing, there are 9 drilling teams moved to new well sites.
Up to 15 March, 13 teams of ZPEC Drilling in Shaanbei area started open drilling and ensured stable operation. There were 5 drilling team finished one well and opened two wells, all of teams were doing efforts for monthly target – 60,000 meters.
copyright © 2021 中曼石油天然气集团股份有限公司 . ALL RIGHTS RESERVED 沪ICP备08116516号-1