On Sep. 21, 2015, the assembly and commissioning of the drilling rig sold to the largest drilling company in Mid east completed.
Since the drilling rig has a nervous operation task, the assemly must be completed within a limited time. With the big support of ZPEC, personnels on site communicated with the client, overcomed various difficulties and completed the 2000HP rig’s assemly and commissioning within 3 weeks, saving valuable time for the drilling operation. The client praised ZPEC for the professional quality, high working efficiency and patient and careful training of our engineers.
Vice president Sistanni,project manager Molaei, drilling supervisor, and rig manager attended the whole process of mast raising up, inspected the ZPEC drilling rig carefully, praised the high quality and advanced driller’s cabin of our rig.